• Affected services/equipment’s
Summary:
Downtime: 3 working hours of downtime for HR, Quality, Intake, PHD and
Dispatch offices in 14th and 15th of January. And 1 working hour of
downtime for Finance department on 17th of January
Corrective actions (actions taken to
recover the affected service):
Cost (cost of equipment used or to be For now 12.500,00 MTs where used to replace one of the
used to recover the affected service): switches. An additional 12.500,00 MTs will be required to restore
the network quality as it was before. i.e. the total cost to replace
the switches is 25.000,00 MTs.
Preventive actions (actions to be Improve the Lightening and Earth protection circuits (project to be
care on to avoid future incidents): developed Maintenance department)
Preventive actions (actions to be care Improve the Lightening and Earth protection circuits (project to
on to avoid future incidents): be developed Maintenance department)
Preventive actions (actions to be care Improve the Lightening and Earth protection circuits (project to
on to avoid future incidents): be developed Maintenance department)
• Main printer
Network card burned.
Downtime:
Corrective actions (actions taken to
recover the affected service):
Preventive actions (actions to be care Improve the Lightening and Earth protection circuits (project to
on to avoid future incidents): be developed Maintenance department)
• Summary of cost